MTI Access Project - Weekly Status w/e 28 November 08

From GCWiki Jump to: navigation, search

[edit] VISAGE

  • Tasking and Requisition completed.
  • Payment made to GERONTIC on Thursday 27th (equals a significant chunck of project funding).

[edit] Project

  • GERONTIC JMB (Wednesday 26th) - highlights include (Details ECI - please speak to [REDACTED] if you'd like more info):
    • Update from GERONTIC on their new organisational structure.
    • Prioritisation of key work (such as BULLROARER Node balancing).
    • Update from GERONTIC on future access and shaping opportunities.
    • Review of new cost model for bandwidth delivery (initial indications are that if this were to be applied now, it would reduce the current rental costs by approx 20%).
  • Project Risk & Issue review held.